长春市坦克学院道路工程
施工方案
施工单位:吉林省宏源路桥有限公司
编制日期:2008年9月16日
目录
第一章:工程概述······································1
第二章:施工总平面布置及施工前准备····················4
第三章:施工总进度计划··································10
第四章:污水排水工程····································20
第五章:雨水排水工程···································26
第六章:路基土方土挖与填方······························32
第七章:石灰土工程
······································36
第入章:二灰碎石工程····································40
第九章:沥青砼工程······································44
第十章:附属工程········································49
第十一章:各工序、机械设备及人员配合情况·················52
第十二章:安全保证措施··································54
第十三章:质量保证措施··································56
第十四章:工期保证措施··································60
第一章工程概述
工程概述
南三环C标道路排水工程,位于人民大街至桥梁引道起点之间,桩号为K2+530~K3+900全长1370米,是长春市2003年重点工程项目“南部路网、西部路网、双阳区域”工程,八路六桥两广场之一。该路段全线地势起伏较大,路线基本沿旧有道路,原有旧路破坏严重,沿线无排水设施,污雨水自然排放,道路两侧有大量的生活及建筑垃圾,且每日不断在增加;建筑物多为民房和大棚。
土壤情况从上到下依次为生活垃圾填土、粉质粘土、中粗砂、基岩、~%,土壤干湿类型为中湿,地下水位类型为孔隙潜水,~,~,。
道路横断面采用两块板形式,机动车道宽12×2米,中间分隔带宽4米,人行步道宽6×2米,×2米,%直线两面坡,人行步道横坡采用2%直线单面坡。
结构设计:机动车道结构:4cm中粒沥青混凝土SBS—16
6cm粗粒混凝土AC—25I
20cm二灰碎石(10:20:70)
20cm石灰粒料土(10:50:40)
20cm石灰土(10:90)
注:K3+580~K3+900段石灰土用12:88配比。
人行步道结构:8cm彩色方砖
4cm(1:3)水泥砂浆
15 cm(10:90)石灰土
在与人民大街道路结构接茬时,新结构压在旧结构上,,顺接平顺,利于行车。
本标段设有污、雨水管线各一道,雨水管线设在沿线道路中心左侧4 m处,污水管线设在道路中心右侧12 m,施工前把原有的电信光缆、电缆、自来水管线调查清楚,作好标记。施工中注意三环路与人民大街交汇处,为不破坏人民大街路面,此段的污水、雨水管线进行顶管施工。
施工场地内外交通情况
本工程起点位于长春市人民大街与南三环路交汇处,终点位于黑咀桥附近,通往临河街,场外交通方便,利于施工场外运输。填挖方分段施工,各段内两侧流水作业,施工中充分利用原有旧路,保证施工车辆场内正常通行。
合同项目
本标段主要工程项目包括:
a 污水排水工程 b 雨水排水工程
c 路基工程 d 路面工程
e 附属构筑物
本工程的主要工程量
主要工程量表
序号
项目名称
单位
工程量
备注
一
道路工程
1
4cm中粒式沥青砼 SBS—16
㎡
33580
2
6cm粗粒式沥青砼 AC—25I
㎡
33427
3
20cm二灰碎石(10:20:70)
㎡
34961
含乳化沥青
4
20cm石灰粒料土(10:50:40)
㎡
14483
5
20cm石灰土(10:90)
㎡
47092
含土基
6
20cm石灰土(12:88)
㎡
8347
7
直边石 30cm高
m
2511
8
曲边石 30cm高
m
195
9
直边石 35cm高
m
2376
10
曲边石 35
南三环施工组织设计 来自淘豆网www.taodocs.com转载请标明出处.