任务号任务负责人开始时间结束时间计划天数完成度已用天数剩余天数 9/5/11 9/12/11 9/19/11 9/26/11 10/3/11 10/10/11 10/17/11 10/24/11 10/31/11 11/7/11 11/14/11 11/21/11 11/28/11 12/5/11 12/12/11 12/19/11 12/26/11 1/2/12 1/9/12 1/16/12 1/23/12 1/30/12 2/6/12
1 任务1 张三 8/08/11 10/19/11 73 75% 55 18
子任务1 8/08/11 8/25/11 18 100% 18 0
子任务2 8/26/11 9/04/11 10 95% 9 1
子任务3 9/24/11 10/05/11 12 54% 6 6
子任务4 10/06/11 10/20/11 15 50% 7 8
2 任务2 李四 10/20/11 12/11/11 53 19% 10 43
子任务1 10/20/11 11/05/11 17 50% 8 9
子任务2 10/20/11 11/05/11 17 30% 5 12
子任务3 11/06/11 11/24/11 19 0% 0 19
子任务4 11/25/11 12/12/11 18 0% 0 18
3 任务3 王五 11/24/11 3/01/12 99 0% 0 99
子任务1 11/24/11 12/10/11 17 0% 0 17
子任务2 12/11/11 12/27/11 17 0% 0 17
子任务3 12/28/11 2/02/12 37 0% 0 37
子任务4 2/03/12 3/02/12 29 0% 0 29