福州左海公园-金牛山城市森林步道(施工)(项目名称) / 标段
招标编号:榕市市政招2014132
投标文件
投标文件内容: 技术文件___
目录
第一章编制依据及范围·····································2
第二章工程概况···········································3
第三章施工部署···········································6
第一节质量、进度、安全目标·······································7
第二节项目管理总体安排···········································7
第三节设备、人员动员周期和设备、人员、材料运到施工现场的方法····10
第四节施工调度···················································10
第四章施工方案··········································11
第一节施工准备···················································11
第二节基础工程施工方案···········································13
第三节钢桁架工程施工方案·········································20
第四节给排水工程施工方案·········································31
第五节电气工程施工方案···········································33
第六节坡道景观工程施工方案·······································39
第五章施工进度计划······································50
附施工进度计划表·············································51
第六章资源供应计划······································52
第七章施工平面布置······································57
附项目部平面布置示意图·······································60
第八章技术组织措施计划··································61
第一节保证进度目标的措施········································
·61
第二节保证质量目标的措施·········································66
第三节分项工程施工质量保证措施···································68
第四节保证安全目标的措施·········································77
第五节保证成本目标的措施·········································89
第六节保证季节施工的措施·········································91
第七节保证环境的措施·············································94
第八节文明施工的措施·············································98
第九章实施难点和对策···································101
第十章其他应注意的事项·································103
第一章编制依据及范围
一、编制依据
1、福州市鼓楼区建设投资管理中心发布的“福州左海公园—金牛山城市森林步道(施工)”招标文件、补遗书、施工图(示范段)设计文件以及施工技术规范、标准等。
2、现行市政、建筑等设计规范、施工技术规范及规程、工程质量检验评定及验收标准,市政工程预算定额等。
3、现场踏勘、实地调查情况。
4、本单位施工同类工程的成功经验。根据我单位对现场的考察调查结合我们的技术能力、机械设备状况、管理水平、施工经验及拟投入本合同段的资源配置。
二、编制原则
1、遵循招标文件条款的原则
在编制施工组织设计的过程中,严格按照招
森林步道及景观工程施工组织设计 来自淘豆网www.taodocs.com转载请标明出处.