封 面 1/13 作者: Pan Hongliang 仅供个人学****br/>Bozshakol Copper Project Clay plant AB 偏跨 E-House 电缆桥架安装脚手架搭设方案 2/13 Method statement of AB side building E-House cable tray installation program scaffolding erection 11373-BD-NFC-3300-MS-OOO-E-0003 0 IFR ORIGINATOR CHECKED APPROVED REV# DATE REASON Li Xinhua Xia Qing Liu Jianhui 目 录 Content 一、 搭设方案 1. Installation Method 二、 风险评估 2. Risk Assessment 三、 安全管理方案 3. Safety Management Method 一、搭设方案 Installation method 概况 根据设计图纸 AB 偏跨内 E-House 下设置了 2000 多米电缆桥架及敷设大量的电缆, 工作面相当大,工作时间持续长,而电缆桥架安装在 10 米的高空上,为了保障工作人员操作的 3/13 安全性及不影响地面设备安装的空间,采取了以下方案搭设脚手架。 Brief As per the design drawing, more than 2000 m cable trays and huge quantity cables shall be installed for E-house of AB side building. Beside part of the trays shall be install in 10m high place; for ensure safety of installation personnel and reduce the influence of installation of equipment on ground, the method of scaffold installation shall be adopt as mentioned below: 编制依据 Codes and references 设计图纸: Design drawings 现场勘测资料 on site survey document 施工准备 preparation works 技术准备 technical preparation 根据设计图纸及现场资料,进行图纸及资料自审和会审工作。 Self check and cross check of drawing 图纸及资料自审、会审后,组织施工班组熟悉施工过程及有关技术要求,结合现场实际情况集中进行一次全面技术交底。 After self check and cross check, organize the construction team to get familiar with the construction process and the relevant technical requirements, and to give a technical disclosure combined with the actual situation.