1. Communications is best described as:
A. an exchange of information.
B. provid
B. identify project risks
C. identify impacts of various risks
D. plan suitable responses
E. B, C and D only
ANS: E
14. Scheduling is the process by which decisions are made concerning:
A. Tasks to be accomplished.
B. Personnel/organization that will be assigned to accomplish the task.
C. Time when the tasks are to be completed.
D. All of the above.
E. A and C only.
ANS: E
15. The basic elements of communication include:
A. Listening, talking and sign language.
B. Communicator, encoding, message, medium, decoding, receiver, and feedback
C. Clarity of speech and good listening habits
D. Reading, writing and listening
E. All of the above
ANS: B
16. Which of the following would most likely increase the accuracy of estimating the project cost?
A. Pricing out the work at lower levels in the work breakdown structure.
B. Using historical data.
C. Talking to people who have worked on similar projects.
D. All of the above.
E.
A and C only.
ANS: D
17. A variance envelope has been established on a project. The envelope goes from +-30% in R&D to +-5% during manufacturing. The reason for
the change in thickness of the envelope is because:
A. The management reserve has been used up.
B. The accuracy of the estimates in manufacturing are worse than the estimates in R & D.
C. Tighter controls are always needed as a project begins to wind down.
D. Of the personal desires of the project sponsor.
E. Of none of the above
ANS: E
18. Cost of quality is:
A. associated with non-conformance to specifications and requirements.
B. primarily caused by poor workmanship of workers who are building or manufacturing the product.
C. used to determine whether a quality management program is suitable for a given project.
D. negligible for most large projects.
E. A and B
ANS: A
19. Manag