Seite 16
Kopf wie Deckblatt, d. h. Logos + Referenzdokumente ------gilt für alle folgenden Seiten! Error! Reference audit on site, where required
Medium requirement
Project work in acc. with APQP method
APQP Status Reports
Project discussion(s), where required
Sampling
Process review/process audit on site, where required
Maximum requirement
Project work in acc. with APQP method
APQP Status Reports (increased number)
Project Review(s)
Sampling
Process review/process audit on-site
PE 3
Standard product
PE 2
Medium risk
PE 1
Increased risk
The supplier is informed of the project classification when the order is issued, at the latest. The customer may change the project classification during the course of the project as a result of unforeseen circumstances.
Should any requirements change during the course of the project, all affected documents, e. g. Control Plan, FMEA, process flow diagram etc., must be changed accordingly.
Seite 16
Kopf wie Deckblatt, d. h. Logos + Referenzdokumente ------gilt für alle folgenden Seiten! Error! Reference source not found.
Quality Assurance Agreement with Production Material Suppliers
S 296001 Part 1
Page 2 of 3
Revision: November 2008
QN / / QSR08112431D
Seite 16 von 3
Ausgabe: April 2003
Project classification PE 1 – Increased risk
The sup