下载此文档

新桥道口安装整体道口板施工组织设计.doc


文档分类:建筑/环境 | 页数:约16页 举报非法文档有奖
1/16
下载提示
  • 1.该资料是网友上传的,本站提供全文预览,预览什么样,下载就什么样。
  • 2.下载该文档所得收入归上传者、原创者。
  • 3.下载的文档,不会出现我们的网址水印。
1/16 下载此文档
文档列表 文档介绍
新桥道口安装整体道口板
施工组织设计
永煤公司铁路运输处
目录
1 工程施工模式·········································································2
2安装整体道口板工程施工方案···············································2
···················································2
···············································3
整体道口板施工··································································3
···································································3
···········································································4
···········································································5
、机具等摆放位置·························································7
···················································8
···················································9
·····································································10
3、施工安全措施·······································································10
·····························································10
·····················································11
·····················································11
4施工所需机具、材料·····························································12
、工器具······························································12
··········································································13
新桥道口安装整体道口板施工组织设计
1 工程施工模式
,位于新桥矿铁路专用线DK6+,现为木枕式橡胶道口板铺面,公路路面宽度12米,公路与铁路为平交,平交道口宽度为12米,由于过往车辆多为拉煤车,载重量大,造成道口铺面板损坏、道口线路病害严重,危极行车安全,为了修复永涡道口破损路面,恢复道口良好状态,保证铁路行车安全,计划对该平交道口铺面进行整体式改造,由铁运处组织施工。
,计划采用购进的钢筋混凝土整体道口板和底板,现场吊装铺设,整体道口板①,宽3米,需4块;②长度为2米/块,宽3米,需1块,合计12米,底板共预制12米,,底板下部用半干混凝土压实找平。道口两侧预埋热熔管,具体数量和位置由电务段确定。
2安装整体道口板工程施工方案

施工组织领导小组
组长:张磊
施工负责人:郑伟
成员:任洪俊李永泉夏飞李亚峰
徐强李汉强杜国昌孟红光
责任分工:
张磊:负责施工管理与协调工作;
郑伟:全面负责施工现场管理工作;
任洪俊:负责施工安

新桥道口安装整体道口板施工组织设计 来自淘豆网www.taodocs.com转载请标明出处.

非法内容举报中心
文档信息
  • 页数16
  • 收藏数0 收藏
  • 顶次数0
  • 上传人86979448
  • 文件大小1.47 MB
  • 时间2017-12-12