项目
12#、14#、15#、16#楼
附着升降脚手架工程施工方案
编制:
审核:
批准:
编制单位:济南四建(集团)有限责任公司脚手架工程公司
年月日
目录
一、编制依据····················································3
二、工程位置及概况··············································3
三、泰山牌JT02-1导轨式液压升降脚手架的概况及技术参数··········3
四、导轨式液压升降脚手架在济南站南货场三区15、16#楼工程施工方案··························································5
架体结构计算··········································5
机位布置··············································8
施工组织安排··········································9
施工工艺流程··········································
9
施工方法及技术要求····································9
架体安装············································10
附着升降脚手架升、降··································15
附着升降脚手架的使用·································17
脚手架拆除··········································19
附着升降脚手架安装质量要求···························19
五、安全措施····················································
20
安全技术要求·········································20
安全组织保障·········································21
安全技术有关规定·····································22
六、施工计划····················································23
1、进度计划··············································23
2、材料与设备计划········································23
3、劳动力计划············································24
七、施工配合····················································24
八、设备使用中常遇到的故障及处理方法····························24
九、附着升降脚手架检查评分表···································25
十、拆除方案···················································27
十一、应急预案·················································34
附图:
机位布置平面图
竖向留孔位置图
附墙支座与建筑物固定详图
脚手架立面图
临时找平架施工图
临时支撑固定导轨主框架详图
断开处架体搭设详图
12#、14#、15#、16#楼
导轨式液压升降脚手架施工方案
编制依据:
1、12#、14#、15#、16#楼的建筑、结构施工设计图纸
2、《建筑施工附着升降脚手架管理暂行条例》建设部建字[2000]230号文
3、《建筑施工扣件式钢管脚手架安全技术规范》GJG130-2001
4、其他国家和地方相关规定。
二、工程概况:
本工程位于济南市经一路178号,12#、14#、15#、16#住宅楼均为剪力墙结构,地上三十四层,。施工外防护脚手架均采用导轨式液压升降脚手架。选用有专业施工资质的单位组织该项脚手架施工。
三、泰山牌JT02-1导轨式液压升降脚手架的概况:
“泰山牌导轨式液压升降脚手架”,于2002年7月8日获得建设部的《科学