管道防腐层修复及缺陷修复(补强)工程- 施工方案
管道防腐层修复及缺陷修复(补强)工程
施工方案
四川盛泽石油工程技术有限公司
二○一三年六月
四川盛泽石油工程技术有限公司
目录
一、工程概况····································································································· 错误!未定义书签。
二、编制依据····································································································· 错误!未定义书签。
三、施工方案及技术措施················································································ 错误!未定义书签。
施工方案························································································ 错误!未定义书签。
主要工程量···················································································· 错误!未定义书签。
防腐层修复技术方案····································································· 错误!未定义书签。
缺陷修复技术方案········································································· 错误!未定义书签。
露管埋深及保护整改技术方案······················································ 错误!未定义书签。
排水沟开挖技术方案····································································· 错误!未定义书签。
护坡保坎施工技术方案································································· 错误!未定义书签。
------------------------------------------------------- [ 1 ] -------------------------------------------------------
四川盛泽石油工程技术有限公司
1、工期进度计划及保证措施
根据目前掌握的现场资料情况来看,计划日历工期145天。计划开竣工日期和施工进度网络图见附表四。
计划控制
依据业主总体网络计划及监理指令,编制施工计划。并根据工程进展情况及时进行调整,保证计划的科学性,使计划的有效性、适宜性、充分性得到评估和保证,确保计划对施工的指导性,使工期处于计划的控制之中。
计划包括:施工计划,劳动力平衡计划,器材需用计划,技术力量配备计划,资金使用计划等。
器材控制
凡计划用于本工程的材料、设备,必须全部按计划就位并专用于本工程,其他任何工程不得挪用。
①施工设备机具的进场就位、转移和转场,均应提前察明路线、环境和障碍,提前作出方案和计划,保证设备机具顺利调遣,作好设备材料运输方案准备工作,避免途中滞留延期。
②作好进货物资检验工作,确保到达施工现场的物资100%合格,杜绝不合格材料用于本工程中。
③作好参加本工程施工设备保养和维修工作,严禁野蛮装卸和使用,保证现场设备完好率100%,一旦现场设备不能满足施工需要,立即把备用设备充实到施工一线。
人员保证
①开工前作好参加本工程施工人员的技术交底、业务培训和健康、安全与环境教育工作。凡计划用于本工程的人员必须全部按计划到岗,不得被随意抽调到其他项目。
②若在施工过程中遇到特殊情况需要支援时,我公司可及时------------------------------------------------------- [ 1 ] -------------------------------------------------------